Milltown Community Centre

Location

Kerry

Client

Nagle Rice Community Centre Ltd.

Sectors

Community

Scale

992m²

Services

Project Management

Brief:

The Community Group had ambitions to develop a multi-functional sports hall to Olympic size and standards. Due to the funding requirements (under the Rural Development Programme) the entire project – including planning – had to be delivered in an extremely tight 18 month time frame.

 

Response:

Corex were appointed to deliver the project and secure the funding drawdown (€500,000). We procured and appointed the design team, oversaw the planning application and managed the construction of the project to a successful conclusion.